The key milestone dates for Phase 2B - The Premier Inn Clinical Building are shown in the timetable below.
                                            
Phase 2B Programme Key Dates
 Stage  Key Date
Phase 2B Enabling works (including moving wards from Cardiac Wing, into newly refurbished areas of the hospital) to commence July 2012 
Phase 2B Enabling works (including moving wards from Cardiac Wing, into newly refurbished areas of the hospital) completed May 2014 
Redevelopment of Cardiac Wing (including refurbishment of levels 2 and 3, and dismantling and rebuilding of floors above) to commence Summer 2014
Redevelopment of Cardiac Wing completed Beginning of 2017
Official opening of The Mittal Children's Medical Centre (Phase 2B) Autumn 2017